Peregrine Energy secures US$168 million for 150MW BESS
Developer Peregrine Energy Solutions has secured US$168 million for a 150MW battery energy storage system (BESS) currently under construction.


Developer Peregrine Energy Solutions has secured US$168 million for a 150MW battery energy storage system (BESS) currently under construction.
Utility and power generation firm Vistra will write down the value of its Moss Landing BESS to the tune of US$400 million in depreciation expense, its entire remaining book value.
Trump’s budget reconciliation bill looks like it could take aim at the current tax credits for downstream clean energy projects, and Clean Energy Associates’ base case is that they will be phased out by the end of the year.
A legal challenge against NextEra Energy Resources (NEER) over the construction of a 250MW/1,000MWh standalone BESS in Georgia has been dismissed by the Superior Court of Fulton County, after several months of litigation.
ESN Premium discusses the ongoing adaptation of EV battery lines to stationary storage applications with Jaehong Park, CEO of LG ES Vertech.
There will be ‘foundational’ shifts in the US’ two largest renewables and energy storage markets this year, California (CAISO) and Texas (ERCOT), significantly affecting battery storage market participation.
In light of lengthy interconnection delays, independent power producer (IPP) NextEra Energy Resources (NEER) has successfully renegotiated the terms of an offtake agreement associated with one of the developer’s solar and storage projects located in Clark County, Nevada.
February 2025 saw around 4.5GW/10.5GWh of grid-scale BESS deployments globally, with China continuing to account for the majority but Europe increasing its share from January.
Samsung SDI will supply energy storage systems (ESS) to US energy holding company and project developer-owner NextEra.
Florida’s largest utility, Florida Power & Light (FPL), is ramping up its energy storage ambitions across the Sunshine State, with plans to deploy over 2.2GW of new BESS between 2026 and 2027.